Project Summary
This project was a complete bumper package, front and rear. 23 tools needed to produce 200 sets of parts.
DFM – The DFM review period was 3 days between our report and the client review. Common design issues identified and adjusted for.
DAY 1 – Project starts, client confirms drawings and mold fabrication begins.
WEEK 8 – Tooling complete, test parts run and shipped to client for review.
WEEK 9 – Client confirms test parts. INDUSTRI-MAN runs 200 sets and ships to the client the same week.